ADU Process & Timeline

A typical ADU project takes 10–14 months from planning to move-in. Timelines vary based on permit processing times, site conditions, and project complexity.

Project Timeline Overview

Month 1
Month 2
Month 3
Month 4
Month 5
Month 6
Month 7
Month 8
Month 9
Month 10
Month 11
Month 12
Month 13
Planning & Permitting16 wks
Planning & Permitting
Site Preparation3 wks
Site Preparation
Foundation3 wks
Foundation
Framing & Structural5 wks
Framing & Structural
Exterior & Waterproofing5 wks
Exterior & Waterproofing
MEP (Mechanical, Electrical, Plumbing)6 wks
MEP (Mechanical, Electrical, Plumbing)
Interior Finishes12 wks
Interior Finishes
Touch Up & Clean7 wks
Touch Up & Clean
Milestones
Project Start
Permit Approved
Foundation Complete
Move-In Ready
Payments

Add estimate for amounts

Deposit
Plans Complete
Permit Issued
Framing Complete
Rough-In Complete
Final Completion
% Paid

Cumulative

Fill in the Cost Estimator to see real dollar amounts.

0%
25%
18%
10%
21%
25%

Planning & Permitting

16 weeks

Feasibility study, design development, plan check submission, and permit approval.

Site Preparation

3 weeks

Demolition, grading, excavation, and utility locating.

Foundation

3 weeks

Forming, pouring, and curing the concrete foundation or slab.

Framing & Structural

5 weeks

Wall framing, roof structure, sheathing, and structural inspections.

Exterior & Waterproofing

5 weeks

Windows, doors, roofing, stucco or siding, and waterproofing membrane.

MEP (Mechanical, Electrical, Plumbing)

6 weeks

Rough-in plumbing, electrical wiring, HVAC ducting, and inspections.

Interior Finishes

12 weeks

Insulation, drywall, flooring, cabinetry, tile, paint, and fixture installation.

Touch Up & Clean

7 weeks

Punch list items, final inspections, deep clean, and certificate of occupancy.

Payment amounts are calculated from your project estimate. Visit the ADU Cost Estimator to see dollar amounts based on your specific project details.

1

Deposit

Week 1$500 deposit

Due at contract signing to begin the design process.

2

Plans Complete

Week 8

Due when architectural drawings are approved and ready for permit submittal.

3

Permit Issued

Week 16

Due when the building permit is issued and construction is ready to begin.

4

Framing Complete

Week 24

Due when structural framing passes inspection.

5

Rough-In Complete

Week 32

Due when all rough mechanical, electrical, and plumbing pass inspection.

6

Final Completion

Week 48

Due at final inspection and certificate of occupancy.

Ready to Get Started?

Every project is unique. Request a free feasibility study and we'll walk you through what your specific timeline looks like.